Planning and consents

The story so far

The application for a Development Consent Order for both DBS projects was approved by the Secretary of State for Energy Security and Net Zero on 14 May 2026. This followed:

  • Engagement with local communities and key stakeholders from 2021.
  • A Development Consent Order application comprising over 1,000 documents.
  • Robust examination by the Planning Inspectorate, including 10 online hearings.

On 14 January 2026, both projects secured routes to market after each was awarded a Contract for Difference (CfD). CfDs are the UK Government's primary mechanism for enabling the deployment of low-carbon electricity at scale, providing long-term price certainty while supporting affordability and security of supply.

Project development timeline

From
2021

Engagement with local communities and key stakeholders begins.

2022
  • Scoping Report submitted to the Planning Inspectorate.
  • Scoping Opinion issued by the Planning Inspectorate.
  • Introductory consultation.
2023
  • RWE entered into Agreements for Lease for the offshore array areas with The Crown Estate.
  • Preliminary Environmental Impact Reports (PEIR) published.
  • Statutory Consultation held.
2024
  • Masdar became a project partner.
  • Development Consent Order submitted and accepted for Examination.
July
2025

Marine Licence Application submitted for Artificial Nesting Structure.

January
2026

Both projects awarded a Contract for Difference (CfD), securing routes to market.

May
2026
  • Development Consent Order approved by the Secretary of State for Energy Security and Net Zero on 14 May.
  • Marine Licence for the Artificial Nesting Structure also approved.