Planning and consents
The story so far
The application for a Development Consent Order for both DBS projects was approved by the Secretary of State for Energy Security and Net Zero on 14 May 2026. This followed:
- Engagement with local communities and key stakeholders from 2021.
- A Development Consent Order application comprising over 1,000 documents.
- Robust examination by the Planning Inspectorate, including 10 online hearings.
On 14 January 2026, both projects secured routes to market after each was awarded a Contract for Difference (CfD). CfDs are the UK Government's primary mechanism for enabling the deployment of low-carbon electricity at scale, providing long-term price certainty while supporting affordability and security of supply.
Project development timeline
From
2021
Engagement with local communities and key stakeholders begins.
2022
- Scoping Report submitted to the Planning Inspectorate.
- Scoping Opinion issued by the Planning Inspectorate.
- Introductory consultation.
2023
- RWE entered into Agreements for Lease for the offshore array areas with The Crown Estate.
- Preliminary Environmental Impact Reports (PEIR) published.
- Statutory Consultation held.
2024
- Masdar became a project partner.
- Development Consent Order submitted and accepted for Examination.
July
2025
Marine Licence Application submitted for Artificial Nesting Structure.
January
2026
Both projects awarded a Contract for Difference (CfD), securing routes to market.
May
2026
- Development Consent Order approved by the Secretary of State for Energy Security and Net Zero on 14 May.
- Marine Licence for the Artificial Nesting Structure also approved.