Current status
DBS is in a period called 'pre-examination' which will be followed by 'examination', 'recommendation' and 'decision'.
Current status:
The Planning Inspectorate published a letter on 24 September 2024 confirming the date of the Preliminary Meeting as 22 October 2024. This letter included a draft timetable for the examination based on it commencing after the close of the Preliminary Meeting.
The Preliminary Meeting began on 22 October 2024 but was adjourned in response to a request from the Examining Authority for additional information. The information was supplied throughout October and November 2024 and on 17 December 2024 the Examining Authority issued a letter outlining a revised draft timetable for a six-month examination process commencing with the Preliminary Meeting that will restart on 14 January 2025.
During the examination phase, Interested Parties are invited to provide more details about their views at hearings, the dates of which are set at the end of the pre-examination period.
The Examining Authority considers all important and relevant matters including the Representations of all Interested Parties, any supporting evidence submitted, and answers provided to the Examining Authority’s questions set out in writing or posed at hearings.
Details about the Preliminary Meeting, Compulsory Acquisition, and Issue Specific Hearings can be found in the Notice of Hearings.
Proposed design changes
We have considered stakeholder feedback received immediately prior to submission of the Development Consent Order and since submission through the Relevant Representation process.
Ongoing design work, combined with the feedback received and a firm grid connection offer, has enabled the team to reduce the footprint of the two proposed onshore converter stations and to reduce and even remove aspects of the proposed offshore infrastructure that are no longer required.
Although the changes are broadly beneficial, they are not significant enough to alter the outcomes of all but one of the offshore environmental assessments, where the impact has been reduced. The effects detailed in the Environmental Statement submitted with the original application, therefore, remain largely unchanged.
Non-statutory consultation relating to these changes took place between 15 November 2024 00:00 and 16 December 2024 23:59.
We will evaluate all the feedback we received before submitting formal Requests for Change to the Examining Authority in January 2025.
The interactive map and ‘Story so far’ web pages will be updated with changes that are accepted into the examination process in early 2025.
Information about the application, the hearings and how to get involved is set out on the PINS Planning Inspectorate website.
Planning Inspectorate websiteRecommendation and decision:
The Planning Inspectorate prepares a report about the application for the Secretary of State for Energy Security and Net Zero. This report will include a recommendation and will be submitted within three months of the close of the examination. The Secretary of State then has a further three months to make the decision on whether to grant or refuse development consent.
Post decision:
Once a decision has been made and published, there is a six-week period in which the decision may be challenged in the High Court. This process of legal challenge is known as Judicial Review.
Other pages you might be interested in
The story so far...
The DBS projects have been through a detailed development phase
About RWE and Masdar
In February 2024, RWE and Masdar joined forces to deliver DBS.
Keep in touch
Get in touch and ask questions with our project team